Kitikyumu-Malivani-Mwanzo Pipeline Extension Water Project

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress100.00%

Location Information

CountyMakueni
ConstituencyMakueni
WardWote/Nziu Wards
SettingUrban
Coordinates-1.799037, 37.585891

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorSuwina Investment Ltd.
ConsultantNone
Target AreasMaii
Scope of Works• Construction of 1no.Closed kiosk • 100.no. Cold Water Consumer Meters • Pipeline Extensions by 7.833 km • Construction of 1no. 100 m3 Masonry Tank • Construction of 1no. 50m3 Elevated Steel Water Tank on 10m High Steel Tower
ImpactsThe project will enhance water access for 6,245 people through 100 consumer meters for efficient distribution.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksProject completed and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 16,844,042.25
GoK Contract SumKES 2,695,046.76
Foreign Contract SumKES 14,148,995.49
Cumulative ExpenditureKES 14,995,504.94
Outstanding CostKES 1,848,537.31

Funding Sources

SourceTypeAmount (KES)
Gok Grant 2,695,046.76
Kfw Grant 14,148,995.49

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 14,148,995.49
2021/22 Approved GOK 2,695,046.76

Beneficiaries

Target Households1,249
Target Population6,245