Project Detail Report
| Status | Completed |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 100.00% |
| County | Kiambu |
|---|---|
| Constituency | Kikuyu |
| Ward | Township/Gitaru/Muguga/Nyathuna |
| Setting | Urban |
| Coordinates | -1.219553, 36.711739 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Stara Supply Enterprise and Vispack Ltd |
| Consultant | None |
| Target Areas | Kikuyu |
| Scope of Works | • 8.32 km Pipeline extension • Construction of 2no. Insitu yard taps • 500no. Cold Water Consumer meters |
| Impacts | The project will enhance water access for 3,500 people through an 8.32 km pipeline extension, 500 consumer meters for efficient distribution, and the construction of two in-situ yard taps for improved community access. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 16,498,587.00 |
|---|---|
| GoK Contract Sum | KES 2,639,773.92 |
| Foreign Contract Sum | KES 13,858,813.08 |
| Cumulative Expenditure | KES 16,498,587.02 |
| Outstanding Cost | KES -0.02 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,639,773.92 |
| Kfw | Grant | 13,858,813.08 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 13,858,813.08 |
| 2021/22 | Approved | GOK | 2,639,773.92 |
| Target Households | 700 |
|---|---|
| Target Population | 3,500 |