Print / Save to PDF
Close
Overview
Status Completed
Type Pipeline extension
Agency Water Sector Trust Fund
Program Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress 100.00%
Location Information
County Mandera
Constituency Mandera South
Ward Elwak North
Setting Urban
Coordinates 2.841188, 40.939539
Timeline & Impact
Start Date 2022-06-04
Planned End Date 2023-06-04
Actual End Date N/A
Contractor Yamha Investment Company
Consultant None
Target Areas Elwak
Scope of Works • 10km pipeline extension
• 300 no. 15mm volumetric meters
• 4 no. water kiosks
Impacts The project will improve water access for 10,000 people through a 10 km pipeline extension, 300 (15mm) volumetric meters for efficient distribution, and four water kiosks for enhanced public access.
Challenges Slow release GOK funds, Slow pace of construction
Remarks None
Project Cost
Total Contract Sum (GoK + Foreign) KES 19,717,281.15
GoK Contract Sum KES 3,154,764.98
Foreign Contract Sum KES 16,562,516.17
Cumulative Expenditure KES 19,646,060.00
Outstanding Cost KES 71,221.15
Funding Sources
Source Type Amount (KES)
Gok
Grant
3,154,764.98
Kfw
Grant
16,562,516.17
Budget Allocations by Fiscal Year
Fiscal Year Stage Funding Side Amount (KES)
2021/22
Approved
FOREIGN
16,562,516.17
2021/22
Approved
GOK
3,154,764.98
Beneficiaries
Target Households 2,000