Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 89.00% |
| County | Nakuru |
|---|---|
| Constituency | Molo |
| Ward | Elburgon |
| Setting | Urban |
| Coordinates | -0.710573, 36.294403 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Heyinz Company Ltd and Noor Consult Ltd |
| Consultant | None |
| Target Areas | Kasarani, Kaloleni, and Matuiku |
| Scope of Works | • 20km Pipeline extension • 800no. 15mm volumetric meters |
| Impacts | The project will enhance water access for 5,490 people through a 20 km pipeline extension and 800 (15mm) volumetric meters, ensuring efficient water distribution and improved service delivery. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 19,624,273.20 |
|---|---|
| GoK Contract Sum | KES 3,139,883.71 |
| Foreign Contract Sum | KES 16,484,389.49 |
| Cumulative Expenditure | KES 19,517,256.55 |
| Outstanding Cost | KES 107,016.65 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 3,139,883.71 |
| Kfw | Grant | 16,484,389.49 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 16,484,389.49 |
| 2021/22 | Approved | GOK | 3,139,883.71 |
| Target Households | 1,098 |
|---|---|
| Target Population | 5,490 |