Oyugis Water Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress80.00%

Location Information

CountyHoma Bay
ConstituencyKasipul
WardCentral Kasipul
SettingUrban
Coordinates-0.509313, 34.730229

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorGlobal Concretes & Construction Co.Ltd
ConsultantNone
Target AreasOyugis
Scope of Works• 8.16km Pipeline extension • 300no. 15mm Volumetric meters
ImpactsThe project will enhance water access for 5,370 people through an 8.16 km pipeline extension and 300 (15mm) volumetric meters, ensuring efficient water distribution and improved service delivery.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,828,116.00
GoK Contract SumKES 3,172,498.56
Foreign Contract SumKES 16,655,617.44
Cumulative ExpenditureKES 18,900,499.88
Outstanding CostKES 927,616.12

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,172,498.56
Kfw Grant 16,655,617.44

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,655,617.44
2021/22 Approved GOK 3,172,498.56

Beneficiaries

Target Households1,074
Target Population5,370