Maraba Kamalambu Pipeline Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress95.00%

Location Information

CountyNandi
ConstituencyTinderet
WardSonghor
SettingUrban
Coordinates-0.018681, 35.274774

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorHeyinz Company Limited
ConsultantNone
Target AreasMaraba
Scope of Works• 13.1km Pipeline extension • Construction of 1no. Closed kiosk • 1no. 100mm Bulk meter • 200no. Cold Water Consumer meters
ImpactsThe project will enhance water access for 2,600 people through a 13.1 km pipeline extension, 200 cold water consumer meters for efficient distribution, one 100mm bulk meter for improved monitoring, and the construction of a closed water kiosk for public access.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,441,177.35
GoK Contract SumKES 3,110,588.38
Foreign Contract SumKES 16,330,588.97
Cumulative ExpenditureKES 19,156,033.99
Outstanding CostKES 285,143.36

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,110,588.38
Kfw Grant 16,330,588.97

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,330,588.97
2021/22 Approved GOK 3,110,588.38

Beneficiaries

Target Households520
Target Population2,600