Jeptulu Town Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress90.00%

Location Information

CountyVihiga
ConstituencyHamisi
WardShaviranga
SettingUrban
Coordinates0.127960, 34.858598

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End Date2025-09-01
ContractorElan Corp Ltd
ConsultantNone
Target AreasJeptulu
Scope of Works• 4.8 km Pipeline extension, • Construction of 1 no. 150 m3 masonry tank, • Construction of 2 no. Closed kiosks, • 250 no. Cold Water Consumer meters
ImpactsThe project will improve water access for 4,753 people through a 4.8 km pipeline extension, 250 cold water consumer meters for efficient distribution, a 150m³ masonry tank for enhanced storage, and two closed water kiosks for public access.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,821,795.00
GoK Contract SumKES 3,171,487.20
Foreign Contract SumKES 16,650,307.80
Cumulative ExpenditureKES 17,417,390.00
Outstanding CostKES 2,404,405.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,171,487.20
Kfw Grant 16,650,307.80

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,650,307.80
2021/22 Approved GOK 3,171,487.20

Beneficiaries

Target Households951
Target Population4,753