Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 90.00% |
| County | Vihiga |
|---|---|
| Constituency | Hamisi |
| Ward | Shaviranga |
| Setting | Urban |
| Coordinates | 0.127960, 34.858598 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | 2025-09-01 |
| Contractor | Elan Corp Ltd |
| Consultant | None |
| Target Areas | Jeptulu |
| Scope of Works | • 4.8 km Pipeline extension, • Construction of 1 no. 150 m3 masonry tank, • Construction of 2 no. Closed kiosks, • 250 no. Cold Water Consumer meters |
| Impacts | The project will improve water access for 4,753 people through a 4.8 km pipeline extension, 250 cold water consumer meters for efficient distribution, a 150m³ masonry tank for enhanced storage, and two closed water kiosks for public access. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 19,821,795.00 |
|---|---|
| GoK Contract Sum | KES 3,171,487.20 |
| Foreign Contract Sum | KES 16,650,307.80 |
| Cumulative Expenditure | KES 17,417,390.00 |
| Outstanding Cost | KES 2,404,405.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 3,171,487.20 |
| Kfw | Grant | 16,650,307.80 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 16,650,307.80 |
| 2021/22 | Approved | GOK | 3,171,487.20 |
| Target Households | 951 |
|---|---|
| Target Population | 4,753 |