Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 90.00% |
| County | Wajir |
|---|---|
| Constituency | Tarbaj |
| Ward | Tarbaj |
| Setting | Urban |
| Coordinates | 2.211714, 40.118167 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | 2024-05-11 |
| Contractor | Ali Galo Traders Ltd |
| Consultant | None |
| Target Areas | Tarbaj |
| Scope of Works | • 5.5 km Pipeline extension • 200 no. 15mm Volumetric meters • 2no. Water kiosks • 1no. Yard taps • 1no. Elevated steel tank 27m2 |
| Impacts | The project will enhance water access for 24,300 people through a 5.5 km pipeline extension, 200 (15mm) volumetric meters for efficient distribution, two water kiosks and one yard tap for improved public access, and a 27m² elevated steel tank for reliable water storage and supply. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 17,324,207.50 |
|---|---|
| GoK Contract Sum | KES 2,771,873.20 |
| Foreign Contract Sum | KES 14,552,334.30 |
| Cumulative Expenditure | KES 17,324,207.50 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,771,873.20 |
| Kfw | Grant | 14,552,334.30 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 14,552,334.30 |
| 2021/22 | Approved | GOK | 2,771,873.20 |
| Target Households | 4,860 |
|---|---|
| Target Population | 24,300 |