Tarbaj Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress90.00%

Location Information

CountyWajir
ConstituencyTarbaj
WardTarbaj
SettingUrban
Coordinates2.211714, 40.118167

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End Date2024-05-11
ContractorAli Galo Traders Ltd
ConsultantNone
Target AreasTarbaj
Scope of Works• 5.5 km Pipeline extension • 200 no. 15mm Volumetric meters • 2no. Water kiosks • 1no. Yard taps • 1no. Elevated steel tank 27m2
ImpactsThe project will enhance water access for 24,300 people through a 5.5 km pipeline extension, 200 (15mm) volumetric meters for efficient distribution, two water kiosks and one yard tap for improved public access, and a 27m² elevated steel tank for reliable water storage and supply.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 17,324,207.50
GoK Contract SumKES 2,771,873.20
Foreign Contract SumKES 14,552,334.30
Cumulative ExpenditureKES 17,324,207.50
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 2,771,873.20
Kfw Grant 14,552,334.30

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 14,552,334.30
2021/22 Approved GOK 2,771,873.20

Beneficiaries

Target Households4,860
Target Population24,300