Chuka/Karingani Water Infrustructure

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress90.00%

Location Information

CountyTharaka Nithi
ConstituencyChuka/Igambang’ombe
WardKaringani
SettingUrban
Coordinates-0.330062, 37.656118

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End Date2024-04-04
ContractorCentura Limited
ConsultantNone
Target AreasChuka
Scope of Works• 11.94km pipeline extension • 720.no 15mm Volumetric metering
ImpactsThe project will improve water access for 8,097 people through an 11.94 km pipeline extension and 720 (15mm) volumetric meters, ensuring efficient water distribution and enhanced service delivery.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,851,966.75
GoK Contract SumKES 3,025,061.60
Foreign Contract SumKES 16,826,905.15
Cumulative ExpenditureKES 7,562,653.99
Outstanding CostKES 12,289,312.76

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,025,061.60
Kfw Grant 16,826,905.15

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,826,905.15
2021/22 Approved GOK 3,025,061.60

Beneficiaries

Target Households1,616
Target Population8,079