Rurie Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress60.00%

Location Information

CountyKirinyaga
ConstituencyMwea
WardWamumu
SettingUrban
Coordinates-0.732747, 37.328417

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorFeight Enterprises Ltd
ConsultantNone
Target AreasMutihti
Scope of Works• Construction of 1 no. closed kiosk • 200no. Cold Water Consumer meters • Pipeline extension by 5.652 km • 1no. 100m3 Elevated storage tank • Construction of a 200m3 CFU
ImpactsThe project will improve water access for 8000 people through a 5.652 km pipeline extension, 200 cold water consumer meters for efficient distribution, a 100m³ elevated storage tank for reliable supply, a 200m³ CFU for enhanced treatment and storage, and the construction of a closed kiosk for public access.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,361,580.00
GoK Contract SumKES 3,097,852.80
Foreign Contract SumKES 16,263,727.20
Cumulative ExpenditureKES 7,375,840.00
Outstanding CostKES 11,985,740.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,097,852.80
Kfw Grant 16,263,727.20

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,263,727.20
2021/22 Approved GOK 3,097,852.80

Beneficiaries

Target Households1,600
Target Population8,000