Majengo Mapya Mtakateni Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress95.00%

Location Information

CountyKilifi
ConstituencyMalindi
WardMalindi town and Iganga
SettingUrban
Coordinates-3.222309, 40.113523

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorMymac Company Ltd.
ConsultantNone
Target AreasMajengo, Mapya and Mtakateni
Scope of Works• 8 km Pipeline extension • Construction of 2 no. yards taps • 130no. 15mm Consumer meters
ImpactsThe project will enhance water access for 6,877 people through an 8 km pipeline extension, 130 (15mm) consumer meters for efficient distribution, and two yard taps for improved public access.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,979,400.00
GoK Contract SumKES 3,196,704.00
Foreign Contract SumKES 16,782,696.00
Cumulative ExpenditureKES 18,451,238.99
Outstanding CostKES 1,528,161.01

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,196,704.00
Kfw Grant 16,782,696.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,782,696.00
2021/22 Approved GOK 3,196,704.00

Beneficiaries

Target Households1,375
Target Population6,877