Kiogoro Water Project

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress55.00%

Location Information

CountyKisii
ConstituencyNyaribari Chache
WardKIOGORO
SettingUrban
Coordinates-0.705347, 34.765662

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorBrooca LTD
ConsultantNone
Target AreasKisii
Scope of Works• 9.4 km Pipeline extension • Construction of 2 no. Closed kiosks • 500no. 15mm Volumetric meters & 500no. 20mm Volumetric meters • 150m3 Elevated steel tank
ImpactsThe project will improve water access for 4,360 people through a 9.4 km pipeline extension, 1,000 volumetric meters (500 at 15mm and 500 at 20mm) for efficient distribution, a 150m³ elevated steel tank for reliable storage, and the construction of two closed kiosks for public access.
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 19,309,722.60
GoK Contract SumKES 3,089,555.62
Foreign Contract SumKES 16,220,166.98
Cumulative ExpenditureKES 14,564,169.52
Outstanding CostKES 4,745,553.08

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,089,555.62
Kfw Grant 16,220,166.98

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 16,220,166.98
2021/22 Approved GOK 3,089,555.62

Beneficiaries

Target Households872