Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 96.00% |
| County | Baringo |
|---|---|
| Constituency | Mogotio |
| Ward | Mogotio |
| Setting | Urban |
| Coordinates | -0.021647, 35.953477 |
| Start Date | 2022-06-04 |
|---|---|
| Planned End Date | 2023-06-04 |
| Actual End Date | N/A |
| Contractor | Slick Solutions Limited |
| Consultant | None |
| Target Areas | Mogotio |
| Scope of Works | • Construction of 3No.yard Taps • 400 No. consumer meters • Pipeline extensions-3,550m • 1 no. 24m3 Elevated steel Water Tank |
| Impacts | The project will enhance water access for 8,770 people through a 3,550m pipeline extension, 400 consumer meters for efficient distribution, a 24m³ elevated steel water tank for reliable storage, and three yard taps for improved public access. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 12,981,664.50 |
|---|---|
| GoK Contract Sum | KES 2,077,066.32 |
| Foreign Contract Sum | KES 10,904,598.18 |
| Cumulative Expenditure | KES 5,192,665.60 |
| Outstanding Cost | KES 7,788,998.91 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 2,077,066.32 |
| Kfw | Grant | 10,904,598.18 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 10,904,598.18 |
| 2021/22 | Approved | GOK | 2,077,066.32 |
| Target Households | 1,754 |
|---|---|
| Target Population | 8,770 |