Bungoma PSF

Project Detail Report

Overview

StatusOngoing
TypePublic Sanitation
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress97.00%

Location Information

CountyBungoma
ConstituencyKanduyi
WardKhalaba
SettingUrban
Coordinates0.568372, 34.561539

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorKemasha Investments Ltd
ConsultantNone
Target AreasBungoma
Scope of WorksStandard PSF and Septic tank
ImpactsThe project will enhance public sanitation for 800 people daily through construction of a Standard PSF
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 6,199,218.90
GoK Contract SumKES 991,875.02
Foreign Contract SumKES 5,207,343.88
Cumulative ExpenditureKES 4,723,214.40
Outstanding CostKES 1,476,004.50

Funding Sources

SourceTypeAmount (KES)
Gok Grant 991,875.02
Kfw Grant 5,207,343.88

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 5,207,343.88
2021/22 Approved GOK 991,875.02

Beneficiaries

Target Households160
Target Population800