Ndhiwa PSF

Project Detail Report

Overview

StatusOngoing
TypePublic Sanitation
AgencyWater Sector Trust Fund
ProgramWater Supply and Sanitation for the Urban Poor -KfW-Phase IV
Progress65.00%

Location Information

CountyHoma Bay
ConstituencyNdhiwa
WardKanyamwa Kologi
SettingUrban
Coordinates-0.730324, 34.365984

Timeline & Impact

Start Date2022-06-04
Planned End Date2023-06-04
Actual End DateN/A
ContractorOkquims General Supplies
ConsultantNone
Target AreasNdhiwa
Scope of WorksStandard PSF and Septic tank
ImpactsThe project will enhance public sanitation for 800 people daily through construction of a Standard PSF
ChallengesSlow release GOK funds, Slow pace of construction
RemarksNone

Project Cost

Total Contract Sum (GoK + Foreign)KES 6,199,218.90
GoK Contract SumKES 991,875.02
Foreign Contract SumKES 5,207,343.88
Cumulative ExpenditureKES 5,713,193.81
Outstanding CostKES 486,025.09

Funding Sources

SourceTypeAmount (KES)
Gok Grant 991,875.02
Kfw Grant 5,207,343.88

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 5,207,343.88
2021/22 Approved GOK 991,875.02

Beneficiaries

Target Households160
Target Population800