Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Water Sector Trust Fund |
| Program | Water Supply and Sanitation for the Urban Poor -KfW-Phase IV |
| Progress | 45.00% |
| County | Elgeyo-Marakwet |
|---|---|
| Constituency | Keiyo North |
| Ward | Kapsowar |
| Setting | Urban |
| Coordinates | 0.672165, 35.507667 |
| Start Date | 2022-07-04 |
|---|---|
| Planned End Date | 2023-07-04 |
| Actual End Date | N/A |
| Contractor | Sinika Engineering Services Limited |
| Consultant | None |
| Target Areas | Kapsio and Kariobangi |
| Scope of Works | • Construction of 1no. Closed kiosk • 10 No. zonal meters and 150 No. consumer meters • Pipeline extensions-14km |
| Impacts | The project will improve water access for 6,464 people through a 14 km pipeline extension, 10 zonal meters for network monitoring, 150 consumer meters for efficient distribution, and the construction of one closed kiosk for public access. |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | None |
| Total Contract Sum (GoK + Foreign) | KES 19,253,325.00 |
|---|---|
| GoK Contract Sum | KES 3,080,532.00 |
| Foreign Contract Sum | KES 16,172,793.00 |
| Cumulative Expenditure | KES 7,334,600.00 |
| Outstanding Cost | KES 11,918,725.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 3,080,532.00 |
| Kfw | Grant | 16,172,793.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 16,172,793.00 |
| 2021/22 | Approved | GOK | 3,080,532.00 |
| Target Households | 1,293 |
|---|---|
| Target Population | 6,464 |