Gongoni Marereni Water Project Phase I

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyWater Sector Trust Fund
ProgramEnding Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Progress100.00%

Location Information

CountyKilifi
ConstituencyMagarini
WardGongoni marereni
SettingRural
Coordinates-2.923302, 40.138235

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorCentury designs
ConsultantNone
Target AreasGongoni
Scope of WorksPreliminaries and general Pipe works New consumer connections Water Kiosks (3No) Contingency
ImpactsImproved access to clean water for more households
ChallengesSlow release GOK funds, Slow pace of construction
RemarksThe project is complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 53,766,063.34
GoK Contract SumKES 14,965,538.00
Foreign Contract SumKES 38,800,525.34
Cumulative ExpenditureKES 53,766,063.34
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 14,965,538.00
Eu Grant 38,800,525.34

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved FOREIGN 38,800,525.34
2022/23 Approved GOK 14,965,538.00

Beneficiaries

Target Households2,446