Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA) |
| Progress | 100.00% |
| County | Baringo |
|---|---|
| Constituency | Baringo Central |
| Ward | Kapropita, Kabarnet |
| Setting | Rural |
| Coordinates | 0.495816, 35.748014 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | 2024-04-08 |
| Contractor | Century designs |
| Consultant | None |
| Target Areas | Kapropita |
| Scope of Works | Magoini 1- 100m3 masonry tank, pump house, Fencing, 0.75kms pipeline, 15m3/hr chlorine doser, 22KW solarisation of the borehole.Magoini 2- Pump house, rehabilitation of 150m3 masonry tank, fencing, 0.9kms pipeline, 12m3/hr chlorine doser, 25KW Solarization of the borehole Kiboino- 100m3 masonry tank, 3.4kms pipeline , fencing, Automated water kiosk, 7.2km chlorine doser, 15.8 KW solarisation of th2e borehole Kisok- Rehabilitation of the pump house, rehabilitation and construction of the rising main, rehabilitation of 100m3 masonry tank, fencing works, automated water kiosk, 20m3/hr chlorine doser, solarisation of the boreholes Kabarnet- Solar booster system at Kabarnet |
| Impacts | Improved access to clean water for more households |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | The project is complete and operational |
| Total Contract Sum (GoK + Foreign) | KES 55,732,047.78 |
|---|---|
| GoK Contract Sum | KES 9,100,000.00 |
| Foreign Contract Sum | KES 46,632,047.78 |
| Cumulative Expenditure | KES 55,732,047.78 |
| Outstanding Cost | KES 8,446,382.97 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 9,100,000.00 |
| Eu | Grant | 46,632,047.78 |
| Target Households | 2,500 |
|---|---|
| Target Population | 12,500 |