Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Water Sector Trust Fund |
| Program | Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA) |
| Progress | 100.00% |
| County | Mandera |
|---|---|
| Constituency | Mandera South |
| Ward | Mandera |
| Setting | Rural |
| Coordinates | 3.934579, 41.857576 |
| Start Date | N/A |
|---|---|
| Planned End Date | 2024-02-08 |
| Actual End Date | 2024-02-08 |
| Contractor | Seya Global ltd |
| Consultant | None |
| Target Areas | mandera south |
| Scope of Works | Solarization of 6 boreholes at Falama Elwak,2No. Water kiosks ,100 new water connections,installation of chlorine doser,100m3 elevated steel tank,laying of 15.5km pipeline |
| Impacts | Improved access to clean water for more households |
| Challenges | Slow release GOK funds, Slow pace of construction |
| Remarks | The project is complete and operational |
| Total Contract Sum (GoK + Foreign) | KES 51,652,428.76 |
|---|---|
| GoK Contract Sum | KES 14,121,774.02 |
| Foreign Contract Sum | KES 37,530,654.74 |
| Cumulative Expenditure | KES 51,652,428.76 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 14,121,774.02 |
| Eu | Grant | 37,530,654.74 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 37,530,654.74 |
| 2021/22 | Approved | GOK | 14,121,774.02 |
| Target Households | 100 |
|---|---|
| Target Population | 500 |