Kaloleni Water supply

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyWater Sector Trust Fund
ProgramEnding Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Progress100.00%

Location Information

CountyTaita-Taveta
ConstituencyVoi
WardKaloleni
SettingRural
Coordinates-3.386892, 38.575988

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End Date2024-05-08
ContractorLohim ltd
ConsultantNone
Target AreasKaloleni
Scope of WorksConstruction of 1Nr concrete storage tank , Pipe works Construction of 2Nr cattle trough ,Pump station-improvement works Construction of ablution Block at kaloleni pumping station , Accompanying measures
ImpactsImproved access to clean water for more households
ChallengesSlow release GOK funds, Slow pace of construction
RemarksThe project is complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 69,973,672.34
GoK Contract SumKES 17,000,000.00
Foreign Contract SumKES 52,973,672.34
Cumulative ExpenditureKES 62,973,672.34
Outstanding CostKES 7,000,000.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 17,000,000.00
Eu Grant 52,973,672.34

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved FOREIGN 52,973,672.34
2022/23 Approved GOK 17,000,000.00

Beneficiaries

Target Households4,702
Target Population23,510