Qarsadamu

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyWater Sector Trust Fund
ProgramHorn of Africa -Ground Water for resillience Programme (HOAGWR)
Progress0.00%

Location Information

CountyMandera
ConstituencyMandera South
WardShimbir Fatuma
SettingRural
Coordinates2.825600, 40.681020

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantAarvee Associates
Target AreasShimbir Fatuma
Scope of WorksProposed scheme. To be updated after completion of designs
ImpactsTo serve the estimated population. Specific to be updated
ChallengesN/A
RemarksProject at the design stage

Project Cost

Total Contract Sum (GoK + Foreign)KES 34,362,673.06
GoK Contract SumKES 0.00
Foreign Contract SumKES 34,362,673.06
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 34,362,673.06

Beneficiaries

Target Households0
Target Population7,200