Rhamu/Giriza

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyWater Sector Trust Fund
ProgramHorn of Africa -Ground Water for resillience Programme (HOAGWR)
Progress0.00%

Location Information

CountyMandera
ConstituencyMandera North
WardRhamu
SettingRural
Coordinates3.949750, 41.244400

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantAarvee Associates
Target AreasRhamu
Scope of WorksProposed scheme. To be updated after completion of designs
ImpactsTo serve the estimated population. Specific to be updated
ChallengesN/A
RemarksProject at the design stage

Project Cost

Total Contract Sum (GoK + Foreign)KES 43,071,119.63
GoK Contract SumKES 0.00
Foreign Contract SumKES 43,071,119.63
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 43,071,119.63

Beneficiaries

Target Households0
Target Population9,700