Narimao water supply

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyWater Sector Trust Fund
ProgramHorn of Africa -Ground Water for resillience Programme (HOAGWR)
Progress0.00%

Location Information

CountyTurkana
ConstituencyTurkana Central
WardKanamkemer
SettingRural
Coordinates3.143433, 35.817104

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantCAS
Target AreasKanamkemer
Scope of Works4No Solar Photovoltaic Pumping (PVP) System for Narimao Community, Kangakimak , Kaitese Community and Kaitese Catholic Boreholes. Supply and installation of 32.857 Km of various HDPE Pipeline sizes ranging from OD 32mm to 140mm and the detailed pressure rating ii. Construction of separate community water point for livestock and domestic use consisting of: • Water kiosks,• Construction of Camel and Cattle Trough,• Construction of Shoats Trough • Individual Connection
ImpactsTo serve the estimated population. Specific to be updated
ChallengesN/A
RemarksProject at the design stage

Project Cost

Total Contract Sum (GoK + Foreign)KES 45,069,081.27
GoK Contract SumKES 0.00
Foreign Contract SumKES 45,069,081.27
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 45,069,081.27

Beneficiaries

Target Households0
Target Population3,348