| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Savana Drillers Co. Ltd |
| Consultant | None |
| Target Areas | Mangu Primary School nd surrounding community |
| Scope of Works | Drilling and test pumping of borehole,
Borehole equipping and solar system, Elevated Steel Tank 24m3 on a 12m High steel Tower,
1 Water Kiosk,
Fencing and Gate and Last Mile Connectivity 5Km |
| Impacts | Increased acess to water to Mangu Primary School and surrounding community |
| Challenges | Delayed project completion. |
| Remarks | Project is 75% complete and stalled contractor given instructions to resume work |