| Start Date | 2020-02-09 |
| Planned End Date | 2021-03-09 |
| Actual End Date | 2023-03-09 |
| Contractor | Lafey Construction Company Limited |
| Consultant | N/A |
| Target Areas | Wote Town
Kwa Nzilu
Kwa Thuvi |
| Scope of Works | • Water Reticulation Network Line 2, Line 3 and Line 4
• Kwa Nzuili to Kwa Thuvi pipeline(Proposed Water Kiosk Point),
• Rehabilitation of the Kamunyolo Treatment Plant,
• Rehabilitation of Kamunyolo-Makueni Boys Rising Main
• Construction of 100m3 Elevated Steel Tank, 12m high at Kamunyolo
• Construction of 5No. Water kiosks with 5m3 plastic tanks on top |
| Impacts | The project serve 9,750 residents (2200 households) of Kwa Thuvi, Muambani and Kwa Francis Mutuku within Wote Town with clean, reliable and adequate water supply |
| Challenges | The project was given a one year extension due to delay in exchequer release |
| Remarks | The project is complete, operational, and has been handed over to the County Government of Makueni |