Wote Water Supply Project Phase I

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyTanathi Water Works Development Agency
ProgramWote Water Supply
Progress100.00%

Location Information

CountyMakueni
ConstituencyMakueni
WardMakueni
SettingUrban
Coordinates-1.776370, 37.620580

Timeline & Impact

Start Date2020-02-09
Planned End Date2021-03-09
Actual End Date2023-03-09
ContractorLafey Construction Company Limited
ConsultantN/A
Target AreasWote Town Kwa Nzilu Kwa Thuvi
Scope of Works• Water Reticulation Network Line 2, Line 3 and Line 4 • Kwa Nzuili to Kwa Thuvi pipeline(Proposed Water Kiosk Point), • Rehabilitation of the Kamunyolo Treatment Plant, • Rehabilitation of Kamunyolo-Makueni Boys Rising Main • Construction of 100m3 Elevated Steel Tank, 12m high at Kamunyolo • Construction of 5No. Water kiosks with 5m3 plastic tanks on top
ImpactsThe project serve 9,750 residents (2200 households) of Kwa Thuvi, Muambani and Kwa Francis Mutuku within Wote Town with clean, reliable and adequate water supply
ChallengesThe project was given a one year extension due to delay in exchequer release
RemarksThe project is complete, operational, and has been handed over to the County Government of Makueni

Project Cost

Total Contract Sum (GoK + Foreign)KES 54,391,427.00
GoK Contract SumKES 54,391,427.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 54,391,427.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 55,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved GOK 30,000,000.00
2022/23 Approved GOK 24,391,427.00

Beneficiaries

Target Households1,950
Target Population9,750