Mavoko Water and Sewer Interventions Extension of Pipeline Phase II & III

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyTanathi Water Works Development Agency
ProgramMavoko Water Supply
Progress100.00%

Location Information

CountyMachakos
ConstituencyMavoko
WardMakadara, Athi River West
SettingUrban
Coordinates-1.449935, 36.985910

Timeline & Impact

Start Date2022-01-07
Planned End Date2024-01-01
Actual End Date2024-01-01
ContractorInvegus Limited
ConsultantN/A
Target AreasNgei KMC Athi River
Scope of Works• 27.8 Km of various sizes water supply pipelines including fittings • 1.8 Km sewer lines • Manholes and valve chamber • Construction of 250 m3 elevated steel tank • Consumer Connection kits • Capacity building for MAVWASCO
ImpactsThe project serve 3,500 households with clean, safe, and affordable water
ChallengesThe project was delayed due to delayed exchequer release
RemarksThe project is complete, operational, and has been handed over to Mavoko Water and Sanitation Company

Project Cost

Total Contract Sum (GoK + Foreign)KES 172,461,307.00
GoK Contract SumKES 172,461,307.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 172,461,307.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 173,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved GOK 100,000,000.00
2023/24 Approved GOK 72,461,307.00

Beneficiaries

Target Households1,240
Target Population6,200