| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Malili Construction and Engineering Works Limited |
| Consultant | N/A |
| Target Areas | Talanduli
Kamuwongo |
| Scope of Works | • Construction of Offtake from the existing Kiambere Mwingi Pipeline
• Laying of 13.6 Km pipeline from Kamuwongo Offtake to Tulanduli primary school
• Construction of 3 No. 225 m3 Masonry tanks
• Construction of 100 m3 steel elevated tank
• Construction of 5 No. water kiosks
• Construction of solar farm, installation of pumping units and associated works |
| Impacts | The project serve 2,000 households with clean, safe, and affordable water |
| Challenges | The project was delayed due to delayed exchequer release |
| Remarks | The project is complete, operational, and has been handed over to Mwingi Water and Sanitation Company |