Equipping of Unii Borehole Water Supply Project

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTanathi Water Works Development Agency
ProgramDrilling and Equipping 40No. Boreholes
Progress100.00%

Location Information

CountyKitui
ConstituencyKitui South
WardIkanga/Kyatune
SettingRural
Coordinates-1.949730, 38.365870

Timeline & Impact

Start Date2022-12-03
Planned End Date2022-10-06
Actual End Date2022-08-09
ContractorLyjos Enterprises Limited
ConsultantN/A
Target AreasCommunity Schools
Scope of Works• Installation of submersible pump, • solar installation with steel mounting structure, • Distribution pipeline • 2No water kiosks,
ImpactsThe project serves the target area with clean, safe, and affordable water
ChallengesThe project was delayed due to delayed exchequer release
RemarksThe project is complete, operational, and has been handed over to the community

Project Cost

Total Contract Sum (GoK + Foreign)KES 6,667,189.00
GoK Contract SumKES 6,667,189.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 6,667,189.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 7,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved GOK 6,667,189.00

Beneficiaries

Target Households264
Target Population1,320