Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Tanathi Water Works Development Agency |
| Program | Water for Schools |
| Progress | 100.00% |
| County | Kajiado |
|---|---|
| Constituency | Kajiado East |
| Ward | Kitengela |
| Setting | Rural |
| Coordinates | -1.477810, 36.973670 |
| Start Date | 2022-08-07 |
|---|---|
| Planned End Date | 2022-06-10 |
| Actual End Date | 2023-04-01 |
| Contractor | All-Fzaan Investment Limited |
| Consultant | N/A |
| Target Areas | School |
| Scope of Works | • Drilling and Equipping of borehole • Distribution for the school • Water Storage tank for the school |
| Impacts | The project serves the target area with clean, safe, and affordable water |
| Challenges | The project was delayed due to delayed exchequer release |
| Remarks | The project is complete, operational, and has been handed over to the community |
| Total Contract Sum (GoK + Foreign) | KES 7,800,102.00 |
|---|---|
| GoK Contract Sum | KES 7,800,102.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 7,800,102.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 8,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2022/23 | Approved | GOK | 7,800,102.00 |
| Target Households | 260 |
|---|---|
| Target Population | 1,300 |