Mavoko Water & Sewerage Interventions - Extension of Pipeline Phase I

Project Detail Report

Overview

StatusCompleted
TypePipeline extension
AgencyTanathi Water Works Development Agency
ProgramMavoko Water Supply
Progress100.00%

Location Information

CountyMachakos
ConstituencyMavoko
WardAthi River, Muthwani
SettingUrban
Coordinates-1.465280, 36.995030

Timeline & Impact

Start Date2021-01-10
Planned End Date2023-01-03
Actual End Date2023-01-03
ContractorInvegus Limited
ConsultantN/A
Target AreasMavoko Gimu City Greatwall gardens Jam City Greenpark area
Scope of Works• laying of 6 Km distribution pipeline • Provision of 300 No. water meters to MAVWASCO. • Capacity building for MAVWASCO
ImpactsThe project serves the target area with clean, safe, and affordable water
ChallengesThe project was delayed due to delayed exchequer release
RemarksThe project is complete, operational, and has been handed over to Mavoko Water and Sanitation Company

Project Cost

Total Contract Sum (GoK + Foreign)KES 31,345,500.00
GoK Contract SumKES 31,345,500.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 31,345,500.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 32,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved GOK 20,374,575.00
2022/23 Approved GOK 10,970,925.00

Beneficiaries

Target Households12,000
Target Population60,000