Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Tanathi Water Works Development Agency |
| Program | Drilling and Equipping 40No. Boreholes |
| Progress | 100.00% |
| County | Makueni |
|---|---|
| Constituency | Kilome |
| Ward | Kiima Kiu |
| Setting | Rural |
| Coordinates | -1.910725, 37.294380 |
| Start Date | 2023-07-01 |
|---|---|
| Planned End Date | 2024-12-01 |
| Actual End Date | 2024-12-01 |
| Contractor | Tenamu Investment Limited |
| Consultant | N/A |
| Target Areas | Kemuama Community and 1No. primary school |
| Scope of Works | • Drilling and equipping 1 No. Boreholes with solar • 2 Km rising main • 2 No. 10 m3 storage tank • Fencing and site auxillary works • 2No. water kiosks |
| Impacts | The project serves the target area with clean, safe, and affordable water |
| Challenges | The project was delayed due to delayed exchequer release |
| Remarks | The project is complete, operational, and has been handed over to the community |
| Total Contract Sum (GoK + Foreign) | KES 8,789,800.00 |
|---|---|
| GoK Contract Sum | KES 8,789,800.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 8,789,800.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 10,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2024/25 | Allocated | GOK | 8,789,800.00 |
| Target Households | 200 |
|---|---|
| Target Population | 1,000 |