Vulueni Secondary School Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTanathi Water Works Development Agency
ProgramWater for Schools
Progress100.00%

Location Information

CountyMakueni
ConstituencyMakueni
WardMbitini
SettingRural
Coordinates-1.776930, 37.399070

Timeline & Impact

Start Date2023-07-01
Planned End Date2024-12-01
Actual End Date2024-12-01
ContractorThedowa Limited
ConsultantN/A
Target AreasVulueni Secondary School
Scope of Works• Drilling and equipping 1 No. Boreholes with solar • 500 rising main • 1 No. 10 m3 storage tank • Fencing and site auxillary works • 1No. water kiosks
ImpactsThe project serves the target area with clean, safe, and affordable water
ChallengesThe project was delayed due to delayed exchequer release
RemarksThe project is complete, operational, and has been handed over to the school

Project Cost

Total Contract Sum (GoK + Foreign)KES 8,100,347.00
GoK Contract SumKES 8,100,347.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 8,100,347.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 8,100,347.00

Beneficiaries

Target Households200
Target Population1,000