Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Tanathi Water Works Development Agency |
| Program | Water for Schools |
| Progress | 100.00% |
| County | Kitui |
|---|---|
| Constituency | Kitui Central |
| Ward | Kitui Township |
| Setting | Rural |
| Coordinates | -1.365980, 38.008420 |
| Start Date | 2023-07-01 |
|---|---|
| Planned End Date | 2024-12-01 |
| Actual End Date | 2024-12-01 |
| Contractor | Tenamu Investment Limited |
| Consultant | N/A |
| Target Areas | Kitui Boys High School |
| Scope of Works | • Construction of a water Tower at kitui High School • 230 rising main • 1 No. 50m3 steel elevated tank |
| Impacts | The project serves the target area with clean, safe, and affordable water |
| Challenges | The project was delayed due to delayed exchequer release |
| Remarks | The project is complete, operational, and has been handed over to the school |
| Total Contract Sum (GoK + Foreign) | KES 10,123,152.00 |
|---|---|
| GoK Contract Sum | KES 10,123,152.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 10,123,152.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 10,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2024/25 | Allocated | GOK | 10,123,152.00 |
| Target Households | 200 |
|---|---|
| Target Population | 1,000 |