Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Pipeline extension |
| Agency | Tanathi Water Works Development Agency |
| Program | Kinanie Water Supply |
| Progress | 95.00% |
| County | Machakos |
|---|---|
| Constituency | Mavoko |
| Ward | Kinanie/ Mathatani |
| Setting | Urban |
| Coordinates | -1.424015, 37.013770 |
| Start Date | 2022-04-07 |
|---|---|
| Planned End Date | 2025-01-03 |
| Actual End Date | N/A |
| Contractor | Perma Structural Engineering |
| Consultant | N/A |
| Target Areas | Kinanie town |
| Scope of Works | • Construction of 25 Km HDPE Pipeline, • Construction of 1,000m3 Reinforced Concrete Tank and • Fencing and Site Auxiliary Works at Tank Site |
| Impacts | The project upon completion will serve the target area with clean, safe, and affordable water |
| Challenges | Delayed exchequer release |
| Remarks | The project ongoing and is within schedule |
| Total Contract Sum (GoK + Foreign) | KES 224,600,640.00 |
|---|---|
| GoK Contract Sum | KES 224,600,640.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 213,370,608.00 |
| Outstanding Cost | KES 11,230,032.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 225,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | GOK | 33,690,096.00 |
| 2022/23 | Approved | GOK | 67,380,192.00 |
| 2023/24 | Approved | GOK | 89,840,256.00 |
| 2024/25 | Allocated | GOK | 33,690,096.00 |
| Target Households | 2,000 |
|---|---|
| Target Population | 10,000 |