| Start Date | 2025-07-07 |
| Planned End Date | 2028-07-07 |
| Actual End Date | 2028-07-07 |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Kasikeu,
Mukaa,
Kitaingo,
Kiou |
| Scope of Works | 1.) Consultancy services
2.) Construction of a rock fill dam at Mikuyuni river.
3.) Construction of a 10,000m3/day Water treatment plant.
4. )Construction of 150km transmission mains anddistribution network for the project area.
5.) Construction of water storage tanks of capacity ranging from 100m3 to 225m3 within the project area |
| Impacts | (i) Project expected to employ 1,500 persons during implementation and 30 personnell during operation
(ii) To serve 30,000 people(6,000 household) |
| Challenges | Lack of funds to commence detailed signs and construction works even though the preliminary designs are ready |
| Remarks | Preliminary Designs Complete |