Kilome / Mikuyu Dam Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeDam
AgencyTanathi Water Works Development Agency
ProgramKonza City Water Supply
Progress2.00%

Location Information

CountyMakueni
ConstituencyKilome
WardKasikeu Mukaa Kiima Kiu Kalonzoni
SettingUrban
Coordinates-2.015546, 37.380478

Timeline & Impact

Start Date2025-07-07
Planned End Date2028-07-07
Actual End Date2028-07-07
ContractorN/A
ConsultantN/A
Target AreasKasikeu, Mukaa, Kitaingo, Kiou
Scope of Works1.) Consultancy services 2.) Construction of a rock fill dam at Mikuyuni river. 3.) Construction of a 10,000m3/day Water treatment plant. 4. )Construction of 150km transmission mains anddistribution network for the project area. 5.) Construction of water storage tanks of capacity ranging from 100m3 to 225m3 within the project area
Impacts(i) Project expected to employ 1,500 persons during implementation and 30 personnell during operation (ii) To serve 30,000 people(6,000 household)
ChallengesLack of funds to commence detailed signs and construction works even though the preliminary designs are ready
RemarksPreliminary Designs Complete

Project Cost

Total Contract Sum (GoK + Foreign)KES 4,500,000,000.00
GoK Contract SumKES 900,000,000.00
Foreign Contract SumKES 3,600,000,000.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households6,000
Target Population30,000