| Start Date | 2025-07-01 |
| Planned End Date | 2028-07-01 |
| Actual End Date | 2028-07-01 |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Ongata Rongai,
Ngong Town and
Kiserian |
| Scope of Works | 1) Laying of 115 Km of pipelines ranging from DN200 mm to DN63 mm;
2) Construction of 8 No. Water Kiosks;
3) Construction of 1 No. 100 m3 Steel elevated tank;
4) Construction of 2 No. solar farms (600 Kw each) with associated electromechanical works;
5) 8,000 No. consumer connections |
| Impacts | (i) Project expected to employ 1,300 persons during implementation and 20 personnell during operation
(ii) serve a population of 156,000 (31,200 households) |
| Challenges | Lack of funds to commences the construction works even though the detailed designs are ready |
| Remarks | preliminary and detailed designs ready |