Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Sewerage |
| Agency | Tanathi Water Works Development Agency |
| Program | eneration Programme (Syokimau, Mlolongo, AthiWater Rpely |
| Progress | 5.00% |
| County | Machakos |
|---|---|
| Constituency | Mavoko |
| Ward | Athi River, Kinanie, Muthwani, Syokimau/Mulolongo, Athi River West, Katani, Kinanie/Mathani, Makadara, and Sophia |
| Setting | Urban |
| Coordinates | -1.424629, 36.975723 |
| Start Date | 2025-01-08 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Athiriver Mlolongo Syokimau Katani |
| Scope of Works | Construction 318.5 Km Sewer trunks and laterals ranging from DN 300 to DN 1950 mm, Waste water treatment plant of capacity 25,000 m3/day, Supply of 3 no. exhauster trucks and installation of 3,000 No. sewer consumer connection kits |
| Impacts | (i) Project expected to employ 1,200 persons during implementation and 18 personnell during operation (ii) 5,000 holdholds to be connected |
| Challenges | Lack of funds to commence detailed signs and construction works even though the preliminary designs are ready |
| Remarks | Preliminary Designs Complete |
| Total Contract Sum (GoK + Foreign) | KES 7,500,000,000.00 |
|---|---|
| GoK Contract Sum | KES 1,500,000,000.00 |
| Foreign Contract Sum | KES 6,000,000,000.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Target Households | 20,000 |
|---|---|
| Target Population | 100,000 |