| Start Date | 2025-01-06 |
| Planned End Date | 2027-01-01 |
| Actual End Date | 2027-01-01 |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | East Africa Portland Housing |
| Scope of Works | • Laying of 50 Km Water supply pipeline,
• Construction of 5 No. elevated steel tanks,
• Laying of 50 Km Sewer line trunks and laterals. |
| Impacts | (i) Project expected to employ 1,400 persons during implementation and 18 personnell during operation
(ii) 2,000 holdholds to be connected |
| Challenges | Lack of funds to commence detailed signs and construction works even though the preliminary designs are ready |
| Remarks | Preliminary Designs Complete |