| Start Date | 2025-01-06 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Isinet community
Public institutions |
| Scope of Works | • Rehabilitation of 1No.spring source at Enkongu spring.
• Solarisation of Nabulaa A borehole
• Replacing 6km of DN 90mm HDPE from Enkongu spring to Isinet
• Construction of 5km DN 63mm HDPE pipeline to Endikir.
• Construction of 2No.community water point and cattle trough at Duka Moja and Endikirr. |
| Impacts | (i) upon completion will serve 3,260 people (650 households)
(ii) Will employ 12 people during construction
(iii) Will permanently employ 4No. Of operators during operation phase |
| Challenges | Lack of funds to commences the construction works even though the detailed designs are ready |
| Remarks | (i)Final designs complete
(ii) EIA complete |