| Start Date | 2017-06-02 |
| Planned End Date | 2018-08-12 |
| Actual End Date | N/A |
| Contractor | COSPIN srl, in JV with Nurovi srl and Idroesse
engineering srl, |
| Consultant | SWS SRL IN JOINT VENTURE WITH HYDEA SPA |
| Target Areas | Baringo Central and Baringo North Sub-counties |
| Scope of Works | 1. Extension of water supply to Kabartonjo, Kaptorokwo, Kabasis, Kituro and Kapkut.
The total length of pipeline to constructed is 47km. .
2. Sewerage system to serve Kabarnet Town CBD comprising of 7km trunk main and
Waste Water Treatment plant of capacity 3000m3/d)
3. Enlargement of spillway and draw off system for the Dam.
4. Construction of 16 No.silt traps along the rivers
5. Purchase and installation of Dam electrical and instrumentation equipments.
6. Construction of a hydro power Generation System.
7. Rehabilitation of the WSP Offices for utilization by Kirandich Water Company
8. Construction of storage tanks with Capacities ranging from 100m3 to 200m3. |
| Impacts | Improve access to water |
| Challenges | Delay in wayleave acquisition
for the sewer lines |
| Remarks | IPC No.2 has been processed and awaiting payment.
IPC.No 3 is under review by the client.
Master list has been approved and contractor is working on the tax exemption for goods and services. |