| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Guangxi Hydropower Construction Company |
| Consultant | GIBB Africa |
| Target Areas | Eldama Ravine,Mogotio and Rongai Sub-counties |
| Scope of Works | Involves the construction of a new35,000m3/day treatment plant complete with a new chemical house, backwash tank and clear water tank.
A total of 235km of pipeline network comprising of raw water main, treated water mains, distribution system and;
29 No storage reservoirs of different capacities.
Population to be served -300,000 people |
| Impacts | Improve access to water |
| Challenges | No challanges |
| Remarks | Expenditure Ksh.2,503,829,244.22.
The project is at 98% complete.
Outstanding works.
Pressure testing
Procurement of technical supplies-motor bikes and lab equipment,bulkwater meters, elevated tank at Kampi ya moto,Fencing of tanks and Power connection to REs Office are ongoing.
Client has commenced final inspection to facilitate Takeover/handover process. Process ongoing.
Note;
Inter-County Water Supply Handover -Takeover process has started. Two teams formed to spearhead the process:
Technical and Liaison.
Technical to spearhead the joint inspection of completed Emkwen tank LMC works with NARWASCO and CHEMWASCO.
Liaison to work on the tariffs to be used the WSPs for transboundary water.
This activity is to be concluded early February 2024. |