Overview
| Status | Ongoing |
| Type | Water Supply |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP) |
| Progress | 92.00% |
Location Information
| County | Narok |
| Constituency | Kilgoris |
| Ward | Kilgoris and Lolgorian |
| Setting | Urban |
| Coordinates | -1.007100, 34.881300 |
Timeline & Impact
| Start Date | 2021-04-01 |
| Planned End Date | 2023-04-01 |
| Actual End Date | N/A |
| Contractor | China State Construction Engineering Company Ltd |
| Consultant | GIBB Africa |
| Target Areas | Kilgoris, Lolgorian and environs |
| Scope of Works | Water distribution network and rehabilitation of existing system
To benefit over 40,000 people |
| Impacts | Improve access to water |
| Challenges | Wayleave acquisition |
| Remarks | The Project is currently 92% complete and preparation for commissioning is ongoing. |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 567,800,586.76 |
| GoK Contract Sum | KES 51,618,235.16 |
| Foreign Contract Sum | KES 516,182,351.60 |
| Cumulative Expenditure | KES 373,265,303.50 |
| Outstanding Cost | KES 223,640,891.90 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
51,618,235.16 |
| Adb |
Loan |
516,182,351.60 |
Beneficiaries
| Target Households | 8,200 |
| Target Population | 41,000 |