Lokichogio DCCs Borehole

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyCentral Rift Valley Water Works Development Agency
ProgramEqualization Fund Project Phase ll
Progress60.00%

Location Information

CountyTurkana
ConstituencyTurkana West
WardLokichoggio
SettingRural
Coordinates4.205566, 34.353531

Timeline & Impact

Start Date2024-03-07
Planned End Date2024-03-10
Actual End DateN/A
ContractorNawia Kenya Limited
ConsultantN/A
Target AreasLokichogio and adjoining areas
Scope of WorksDrilling, Equipping and Civil Works with elevated tower
ImpactsImprove access to water
ChallengesNo challenges
RemarksWorks ongoing

Project Cost

Total Contract Sum (GoK + Foreign)KES 10,873,642.50
GoK Contract SumKES 10,873,642.50
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,873,642.50

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 10,873,642.50

Beneficiaries

Target Households600
Target Population3,000