Overview
| Status | Ongoing |
| Type | Water Supply |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Equalization Fund Project Phase ll |
| Progress | 80.00% |
Location Information
| County | Turkana |
| Constituency | Turkana Central |
| Ward | Kalokol |
| Setting | Rural |
| Coordinates | 3.528457, 35.858247 |
Timeline & Impact
| Start Date | 2024-03-07 |
| Planned End Date | 2025-03-01 |
| Actual End Date | N/A |
| Contractor | Rotalink Engineering Company Limited |
| Consultant | N/A |
| Target Areas | Wadach, Lobotoo, Ngabeiyatunga, Napeget, Nabulon villages |
| Scope of Works | 32KM pipeline extension |
| Impacts | Improve access to water |
| Challenges | No challenges |
| Remarks | Works ongoing |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 72,624,200.00 |
| GoK Contract Sum | KES 72,624,200.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 36,400,000.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
72,624,200.00 |
Budget Allocations by Fiscal Year
| Fiscal Year | Stage | Funding Side | Amount (KES) |
| 2024/25 |
Allocated |
GOK |
72,624,200.00 |
Beneficiaries
| Target Households | 600 |
| Target Population | 3,000 |