Narengewoi (Nalekan) Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyCentral Rift Valley Water Works Development Agency
ProgramEqualization Fund Project Phase ll
Progress100.00%

Location Information

CountyTurkana
ConstituencyTurkana North
WardLake zone
SettingRural
Coordinates3.150000, 35.350000

Timeline & Impact

Start Date2024-03-07
Planned End Date2024-03-10
Actual End Date2024-05-11
ContractorBretal Limited
ConsultantN/A
Target AreasNarengewoi and adjoining arease
Scope of WorksConstruction of 100m3 masonry Tank, 2No. Kiosks, 2 No. Troughs and 8.4km pipeline extension
ImpactsImprove access to water
ChallengesNo challenges
RemarksCompleted and handed over to the community

Project Cost

Total Contract Sum (GoK + Foreign)KES 9,453,180.98
GoK Contract SumKES 9,453,180.98
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 9,003,029.50
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 9,453,180.98

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 9,453,180.98

Beneficiaries

Target Households1,400
Target Population7,000