Nyalilbuch Borehole Water project

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyCentral Rift Valley Water Works Development Agency
ProgramRehabilitation of Water Supply
Progress100.00%

Location Information

CountyBaringo
ConstituencyMogotio
WardMogotio
SettingRural
Coordinates-0.021562, 35.956518

Timeline & Impact

Start Date2024-04-04
Planned End Date2024-03-06
Actual End Date2024-03-06
ContractorN/A
ConsultantN/A
Target AreasNyalilbuch and adjoining areas
Scope of WorksRehabilitation Works for Nyalilbuch Borehole
ImpactsImprove access to water
ChallengesNo challanges
RemarksSubstantial completion certificate was issued

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,025,165.00
GoK Contract SumKES 1,025,165.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 1,025,165.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 1,025,165.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 1,025,165.00

Beneficiaries

Target Households500
Target Population2,500