Naisoya Pri. School Borehole water project

Project Detail Report

Overview

StatusCompleted
TypeWater Supply
AgencyCentral Rift Valley Water Works Development Agency
ProgramRehabilitation of Water Supply
Progress100.00%

Location Information

CountyNarok
ConstituencyNarok North
WardNarok
SettingRural
Coordinates-0.930027, 35.860020

Timeline & Impact

Start Date2024-09-05
Planned End Date2024-10-08
Actual End Date2024-10-08
ContractorBrookes Contracting Limited
ConsultantN/A
Target AreasNaisoya Pri. School Borehole water project
Scope of WorksConstruction of 3No Water Kiosks, 4.6km pipeline extension and rehabilitation of 2No Water Kiosk
ImpactsImprove access to water
ChallengesNo challenges
RemarksWorks complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 4,924,510.80
GoK Contract SumKES 4,924,510.80
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 4,421,728.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 4,924,510.80

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 4,924,510.80

Beneficiaries

Target Households400
Target Population3,500