Nyaunyau Water Pan

Project Detail Report

Overview

StatusCompleted
TypeWater Pan
AgencyCentral Rift Valley Water Works Development Agency
ProgramGoK Directly Funded Projects
Progress100.00%

Location Information

CountyBaringo
ConstituencyTiaty East
WardLoyamorok
SettingRural
Coordinates0.867251, 36.091816

Timeline & Impact

Start Date2023-07-11
Planned End Date2024-07-02
Actual End Date2024-07-02
ContractorN/A
ConsultantN/A
Target AreasNyaunyau and adjoining areas
Scope of WorksConstruction of 10,800 m3 pan
ImpactsImprove access to water
ChallengesNo challenges
RemarksCurrently in use

Project Cost

Total Contract Sum (GoK + Foreign)KES 4,926,926.00
GoK Contract SumKES 4,926,926.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 4,692,310.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 4,926,925.50

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 4,926,925.50

Beneficiaries

Target Households600
Target Population3,000