Overview
| Status | Completed |
| Type | Water Pan |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | GoK Directly Funded Projects |
| Progress | 100.00% |
Location Information
| County | Baringo |
| Constituency | Tiaty East |
| Ward | Tangulbei |
| Setting | Rural |
| Coordinates | 0.800033, 36.277829 |
Timeline & Impact
| Start Date | 2024-10-04 |
| Planned End Date | 2025-04-04 |
| Actual End Date | 2025-04-04 |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Tangulbei Water Pan |
| Scope of Works | Construction of 18,0000m3 water pan |
| Impacts | Improve access to water |
| Challenges | No challenges |
| Remarks | Project 100% complete. |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 9,062,550.00 |
| GoK Contract Sum | KES 9,062,550.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
9,062,550.00 |
Budget Allocations by Fiscal Year
| Fiscal Year | Stage | Funding Side | Amount (KES) |
| 2023/24 |
Approved |
GOK |
9,062,550.00 |
Beneficiaries
| Target Households | 400 |
| Target Population | 2,000 |