Overview
| Status | Proposed |
| Type | Spring |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Projects For FY 2024/2025- Under Planning and Design |
| Progress | 0.00% |
Location Information
| County | Laikipia |
| Constituency | Laikipia West |
| Ward | Gituamba |
| Setting | Rural |
| Coordinates | 0.381955, 36.290203 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Gatirima community and its environs |
| Scope of Works | Development of 5no springs, pipework, and construction of 150m3 masonry tank |
| Impacts | Improved access to water |
| Challenges | Not commenced |
| Remarks | Under Design |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 400 |
| Target Population | 2,000 |